Compass Mining is pleased to provide the following facility updates for June 26, 2023.

Summer mining is now here! Please note that many facilities will curtail activities during the day due to high local demand on grids.

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime or general information about one of Compass’s partner facilities
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations

Helpful links:

  • Your Compass Dashboard for your order information
  • Compass Status page for real-time updates on facility status
  • Naming conventions for each facility here

Facility Updates

Texas 5: The site is coming back online after repair work was completed Monday. Please expect curtailment events.

Florida 1: Certain units have been pulled from the site for transfer to Texas 5, following cleaning at our Denver Service Center. All clients affected were contacted via email.

Indiana 1 & 2: Heat issues persist. The site is working on rearranging more units to mitigate airflow concerns.

Ontario 1: The site is rearranging units to remove stagnant, hot air trapped in certain sections of the facility. We expect the airflow to be fixed early next week.

Deployment Updates

Bundles:

LoneStar 2: No additional units were deployed last week. Unit 6 is 75% deployed. Deployments will continue as units are energized in Texas 3 and Texas 5.

Next Generation Bundle and/or S19 XP Single Orders: No additional units were deployed last week. Remaining orders remain on standby. Unit allocations may go to alternative sites, depending on the best timeline for units to be energized.

Singles:

Antminer S19j Pro 100TH - Texas Sept. 2022: No additional units were deployed last week. Batch is 91% Deployed. Deployments will continue as units are energized in Texas 3, with 90 left to deploy.

Relocation Updates

South Carolina 2 Relocation: 1,200 units are now on-site, minus a cohort of Whatsminers still being processed at our Denver Service Center. Units will be energized once the site’s breaker issue is resolved.

Redeployed S19 XP (Former Texas 4 units): Over 300 units have been processed at our Service Center, with about 700 more to go.

Please join our client town hall on Tuesday, June 27th to hear from our operations team by filling out the form here.