Below is a live status page for the Texas 3 deployment based on information from the site operator.

🟢 10:00 am EST, March 1 : Another 2,000 units are online, but need configurations.

We are now deprecating support for this page, and will update individual bundle and purchased on our Facility Update blogs, published weekly.


🟢 2:00 pm EST, February 20: 16,000 units or 50 MW are now deployed.

Additional deployments are on hold until electrical outages from last week can be addressed. About 60% of units deployed are back online after a few outages last week.

The on-site team further plans to re-organize some containers to optimize uptime. Please expect downtime during this period once re-organization begins. We will notfiy clients via the status page when the period begins.

Two additional containers are planned for deployment by end of week, depending on progress between electrical maintenance and organization.


🟢 2:00 pm EST, February 10: 16,000 units or 50 MW are now online. We continue to configure units to client pools and are awaiting information for next steps for the final containers.


🟢 11:00 am EST, February 7: A further 8 MW have come online, for a total of 48 MW of allocations 60 MW. We are actively configuring units to pools.


🟢 9:00 am EST, January 25: Units are actively being configured to client pool accounts. No new units will come online this week as the site readies the final 20 MW.


🟢 5:00 pm EST, January 23: 40 MW of the final 60 MW are now online at Texas 3. The on-site team continues to configure client units.


🟢 9:30 am EST, January 19: An additional 10 MW of units went live yesterday afternoon and evening at Texas 3. We are actively working on configurations. Please be aware units may come on and offline as units are energized and configured.

A mix of VIP Bundles (US and R-NA) Unit 9s, Oklahoma 2 redeployments and S19j Pro units have gone online in the 10 MW load. Units are actively being configured.


🟢 10:30 am EST, January 17: The next tranche of units are set for energization today.


🟢 9:30 am EST, January 16: No units will be powered on today due to the Federal holiday. We expect the next tranche to go live tomorrow.


🟢 1:00 pm EST, January 13: The first set of units are back online. We have received word that no more units will be powered on today, but are now scheduled for Tuesday, after the Federal holiday on January 16.


🟢 6:00 pm EST, January 11: Network hardware was delivered today and installed. The on-site team is working to bring units back online to pre-outage levels tomorrow and then further energizations on Friday, depending on the networking issues being resolved.


🟢 9:30 am EST, January 10: The networking issues have been identified as hardware errors. New hardware is set for delivery mid-week, meaning no units will go online until Thursday or Friday of this week.

The site operator continues to deploy additional units as the networking issues are resolved.


🟢 11:00 am EST, January 9: The network has been identified, but unresolved. The on-site team is working to resolve the issue as fast as possible in order to bring more units online. No additional units will be brought online today or tomorrow due to the networking errors. We are working with the on-site team to rectify the situation.


🟢 2:00 pm EST, January 5: The network issue has been identified. However, no additional units will go online today as the issue is patched.


🟢 12:51 pm EST, January 5: A network issue was uncovered yesterday, possibly delaying configuration of next tranche. A further update from the site operator is expected today.


🟢 12:30 pm EST, January 3: A further 7 MW will be energized tomorrow. We are meeting with the site operator today to  schedule out the remaining containers for energization this week.


🟢 10:00 am EST, January 2: The on-site team is offline for the Federal holiday. About 21 MW of units were energized last week. The majority of deployed units are now configured to users pool accounts.

Some units from Lone Star Bundle (1) Unit 5, Mini Bundle Unit 5 and Lone Star (2) Unit 3 are now live. Please expect an email communication as your units go live.


🟢 3:30 pm EST, December 30: Energization of 21 MW is underway with no issues, with the majority of S19j Pros now deployed. We continue to manually configure units to proper pool accounts.

We are working with the on-site operator to finalize the date and time for the next tranches to go online.


🟢 1:30 am EST, December 29: We have begun unit configurations for the 15 MW of deployed units (majority are S19j Pro units). An additional 6 MW of units are slated for energization tomorrow.

The site inspection revealed issues with one transformer due to the recent winter storm. This does not impact energization for the units tomorrow.


🟢 12:30 pm EST, December 28: The first units have begun turning on. We are waiting on unit information to begin configurations.


🟢 5:30 pm EST, December 27: The site operator will energize 15 megawatts (MW) of Compass Mining units tomorrow beginning at 11 AM CST. Further units will be brought online this week as the energy provider evaluates the site following the winter storm.


🟢 12:40 pm EST, December 27: Constellation Energy has been inspecting the site following the winter storm and found no major issues so far. The next tranche of units are slated for energization Wednesday, December 28.


🟢 10:20 am EST, December 23: The next tranche of units is scheduled for energization by the end of next week, following the winter storm and US Federal Christmas holiday.