Compass Mining is pleased to provide the following facility updates for March 27, 2023

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime or general information about one of Compass’s partner facilities.
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.

Helpful Links:

  • Your Compass Dashboard for your order information.
  • Compass Status page for real-time updates on facility status.
  • Naming conventions for each facility here.

Facility Updates

Texas 3: Oklahoma 2 redeployments, MINI Bundle Unit 5 & 6, Lonestar Bundle 1 & 2, VIP Bundle, R-NA bundle units, M30S++ and S19j Pro singles are all slated to come online at Texas 3.

About 53 MW are online of the final 60 MW. We continue to wait for further energization of remaining containers for full site deployment. Please refer to the deployment updates below for more information on your specific product.

Repairs on troubled miners continue at Texas 3, with over 500 repaired and 1,000 total diagnosed. A Bitmain team will be on site shortly to expedite the process.

Units in line for or completed repair at Texas 4.

Texas 4: About 500 units were impacted by needed repairs at Texas 4, including about 300 S19 XPs.

Some 300 repairs are now done. We are proceeding through units by batches, beginning with those still under warranty. We expect to be finished with the entire project within the next 2-3 weeks.

Please refer to this recently published report on S19 XPs for further information on the repair issue.

Manitoba 1: Units are now moving to Manitoba 9 after the decision to wind down operations at Manitoba 1. We remain on track for redeployment by early April and will continue to update clients by email.

Deracking and reracking Manitoba.

Minnesota 1: The site is now back online, ahead of schedule after swapping out the failed breaker. If you have a unit offline from Minnesota 1, please file a support ticket.

South Carolina 2: Units are now offline and are prepping for servicing and shipment. We remain on schedule for redeployment in late April.

Deployment Updates

Mini Bundle 1: Mini Bundle Unit 5 is complete minus a small minority of 3 units soon to come online at Texas 3. Unit 6 deployment is 53% complete and will continue as containers are energized in Texas 3.

LoneStar 1: Unit 6 is 99% deployed with the remaining few customers awaiting the correct model type.

LoneStar 2: Unit 5 is 97% deployed with the remaining 3% awaiting the correct model type. Unit 6 is in queue for deployment following Mini Bundle 1 U6.

US-VIP: Unit 7 and 9 have been deployed in Texas 3. Clients were offered a free upgrade for Unit 8 to an S19J Pro 92TH for all clients who agree to hosting in Texas 4. Units 10 is 91% deployed, and 11-12 will be deployed in Texas 3 once additional containers are energized.

RU-VIP: Unit 8 has been deployed in Texas 3. Unit 10 is now 70% deployed. Units 10-12 will be deployed in Texas 3 once additional containers are energized.

Next Generation Bundle and/or S19 XP Single Orders: Units are in queue for deployment in Texas 3. Please file a support request if you’d like to go online earlier at Ontario 1 or a Manitoba site with your Next Generation Bundle and/or S19 XP Single Order at a hosting rate of $0.079. We continue to wait on additional hosting capacity at Texas 3 to place these units online.

KA3: All December and January and some February orders of KA 3 are online at Ontario 1. We continue to wait for units with a March online date to be delivered from Bitmain.

We are seeing higher failure rates (dead on arrival) units once deployed to the facilities. We are working with the facilities to hard reboot these units or send them back to Bitmain for replacement if necessary. You will be contacted individually if an issue arises with your unit.

We have Bitmain staff onsite to help troubleshoot units going online.

L7: Some January L7’s online dates are now online. A few are needing servicing after being found defective from the manufacturer. Please expect a ticket from our team if your unit was affected. All February and later online dates for L7s are awaiting word from Bitmain for delivery.

We have Bitmain staff onsite to help troubleshoot units going online.

We have received the next batch of units from Bitmain and are beginning to ship them from Hong Kong.

Texas 4 S19j Pro 100: Batch is 80% deployed. Remaining units will be deployed once energized.

Ontario S19j Pro 100: Customers were assigned temps, worker names starting with “ttx.” These units will hash to customers until their permanent unit is available. Email communications will be received for both the temp assignment and the permanent unit assignment.