Compass Mining is pleased to provide the following facility updates for February 20, 2023

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime or general information about one of Compass's partner facilities.
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.

Helpful Links:

  • Your Compass Dashboard for your order information.
  • Compass Status page for real-time updates on facility status.
  • Naming conventions for each facility here.

Facility Updates

Texas 3: Oklahoma 2 redeployments, MINI Bundle Unit 5 & 6, Lonestar Bundle 1 & 2, VIP Bundle, R-NA bundle units, M30S++ and S19j Pro singles are all slated to come online at Texas 3.

We currently have ~50 megawatts (MW) or 16,000 units online, of the deployment complete.

An electrical outage from last week is partially fixed, with about 60% of the facility back online. We are working with the facility to bring the rest of the deployed miners back online as soon as possible.

The next unit deployments are planned for after the electrical outage is fixed and some containers are reorganized for better uptime.

Texas 2: Units have been powered off, with each client receiving a temporary unit from the site operator. We expect the transition to last until mid-March.

Deployment Updates

Mini Bundle 1: Mini Bundle Unit 5 is complete minus a minority of units soon to come online at Texas 3. Unit 6 deployment is over 40% complete and will continue as containers are energized.

LoneStar 1: This bundle is over 99% deployed except for a small minority of units soon to come online at Texas 3.

LoneStar 2: Unit 5 is deployed. Unit 6 is 11% deployed and in queue for deployment following Mini Bundle 1 Unit 6.

US and RU VIP: Unit 7 and 9 have been deployed in TX3. Unit 8 was given a free upgrade to an S19J Pro 92TH and has been deployed for all clients opting in to Texas 4.

Next Generation Bundle and/or S19 XP Single Orders: Units are in queue for deployment with target of mid-February through mid-March, depending on order date.

KA 3: Some units have been received from Bitmain, but are still waiting on the majority of units to be delivered from the manufacturer. Customers will be deployed chronologically by purchase date. The first of these units are expected to come online Feb. 28. Please expect a further 3-4 weeks until all units are deployed. Further communications will continue via email.